The “turn-around” time of a user job is the |
A. | time since its submission to the time its results become available. |
B. | time duration for which the CPU is allotted to the job. |
C. | total time taken to execute the job. |
D. | time taken for the job to move from assembly phase to completion phase. |
Answer» D. time taken for the job to move from assembly phase to completion phase. | |