1. |
At time 0, an OS with round-robin scheduling (time quantum = 5 units) has 5 processes P1, P2, P3, P4, P5 with burst times 15, 10, 20, 5, 15 respectively. What is the average turn-around time? |
A. | 40 units |
B. | 46 units |
C. | 56 units |
D. | 65 units |
Answer» C. 56 units | |