The_time_required_to_spin_the_desired_sector_under_the_read/write_head,_once_the_read/write_head_is_positioned_on_the_desired_track.$

A. Seek time
B. Arrival rate
C. Latency
D. Transfer rate
Answer» D. Transfer rate