1.

The time required for two operations cutting and binding for 5 jobs are as follows:Job No.12345Cutting (min)86257Binding (min)87764What is the optimal makespan sequence?

A. 2-4-1-3-5
B. 3-4-2-1-5
C. 1-2-3-4-5
D. 3-5-2-4-1
Answer» C. 1-2-3-4-5