| 1. |
The time required for two operations cutting and binding for 5 jobs are as follows:Job No.12345Cutting (min)86257Binding (min)87764What is the optimal makespan sequence? |
| A. | 2-4-1-3-5 |
| B. | 3-4-2-1-5 |
| C. | 1-2-3-4-5 |
| D. | 3-5-2-4-1 |
| Answer» C. 1-2-3-4-5 | |