1.

The time for a clay layer to achieve 85% consolidation is 10 years. If the layer was half as thick, 10 times more permeable and 4 times more compressible then the time that would be required to achieve the same degree of sonsolidation is

A. 1 year
B. 5 years
C. 12 years
D. 16 years
Answer» B. 5 years