A borrow pit soil has a dry density of 17 kN/m3. How many cubic meters of this soil will be required to construct an embankment of 100 m3 volume with a dry density of 16 kN/ m3

A. 94 m
B. 106 m
C. 100 m
D. 90 m
Answer» B. 106 m