1.

The slope and level detector circuit in a CRO has a delay of 100 ns. The start-stop sweep generator has a response time of 50 ns. In order to display correctly, a delay line of

A. 150 ns has to be inserted into the y-channel
B. 150 ns has to be inserted into the x-channel
C. 150 ns has to be inserted into both x and y channel
D. 100 ns has to be inserted into both x and y channel
Answer» B. 150 ns has to be inserted into the x-channel


Discussion