The shortest possible time in which an activity can be achieved under ideal circumstances is known as |
| A. | pessimistic time estimate |
| B. | optimistic time estimate |
| C. | expected time estimate |
| D. | the most likely time estimate |
| Answer» C. expected time estimate | |