The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f , respectively, areActivityPredecessorsDuration (days)a-2b-4ca2db3ec2fc4gd,e5 |
| A. | 0 and 4 |
| B. | 1 and 4 |
| C. | 2 and 3 |
| D. | 3 and 1 |
| Answer» C. 2 and 3 | |