1.

The perimeter of a circular channel section is 18.84m, calculate the discharge through the channel when it is running full having a bed slope of 1 in 1500 and C = 60.

A. 53.62 m<sup>3</sup>/s
B. 63.62 m<sup>3</sup>/s
C. 73.62 m<sup>3</sup>/s
D. 83.62 m<sup>3</sup>/s
Answer» B. 63.62 m<sup>3</sup>/s