1.
The performance of a specific task in CPM is known as
A.
Dummy
B.
Event
C.
Activity
D.
Contract
Answer» D. Contract
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
Break-even analysis consists of
An activity of the project is graphically represented by ________ on the network diagram.
Pick up the correct statement about relationship between various floats
PMTP (predetermined motion time systems) include
Routing assists engineers in deciding in advance
In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:
The amount deducted from the salary of workers towards employee s provident fund is
The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store
Micro motion study is
Travel charts provide
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply