The operating velocity in the absorption tower is usually 40-50% of the flooding velocity. Packed absorption towers are normally designed for a pressure drop of about _________________ mm of water column per metre height of packing? |
A. | 1-5 |
B. | 20-40 |
C. | 100-150 |
D. | 1000-1500 |
Answer» C. 100-150 | |