The normal flows on two approach roads at an intersection are respectively 500 pcu/h and 300 pcu/h. The corresponding saturation flow is 1600 pcu/h on each road. The total lost time per single cycle is 16 s. The optimum cycle time by Webster’s method is |
| A. | 72.5 s |
| B. | 58.0 s |
| C. | 48.0 s |
| D. | 19.3 s |
| Answer» C. 48.0 s | |