| 1. |
The man-hours required (Tn) to manufacture the nth unit in a plant is given by Tn = T1 nb, where b = -0.322 at the 80% learning rate. If the manufacturing time for the first unit (T1) is 80 man-hours, the total time (in man-hours) required to manufacture the first 4 units, at 80% learning rate, is |
| A. | 322.11 |
| B. | 251.35 |
| C. | 103.76 |
| D. | 51.19 |
| Answer» C. 103.76 | |