| 1. |
The kind of canal section involved in irrigation work is __________ |
| A. | canal high in embankment in partly in excavation |
| B. | canal partly in excavation and partly in embankment |
| C. | canal less in embankment |
| D. | canal half in excavation |
| Answer» C. canal less in embankment | |