The four walls and ceiling of a room of length 25 m, breadth 12 m and height 10 m are to be painted. Painter A can paint 200 m2 in 5 days, Painter B can paint 250 m2 in 2 days. If A and B work together, they will finish the job in: |
| A. | 6 days |
| B. | \(6\frac{10}{33}days\) |
| C. | \(7\frac{10}{33}days\) |
| D. | 8 days |
| Answer» C. \(7\frac{10}{33}days\) | |