The following are the starting and ending times of activities A, B, C, D, E, F, G and H respectively in chronological order: as bs cs ae ds ce es fs be de gs ee fe hs ge he. Here, xs denotes the starting time and xe denotes the ending time of activity X. We need to schedule the activities in a set of rooms available to us. An activity can be scheduled in a room only if the room is reserved for the activity for its entire duration. What is the minimum number of rooms required? |
A. | 3 |
B. | 4 |
C. | 5 |
D. | 6 |
Answer» C. 5 | |