The following are involved in arriving at a unit hydrograph:1. Estimating the surface runoff in depth2. Estimating the surface runoff in volume3. Separation of base flow.4. Dividing surface runoff ordinates by depth of runoffThe correct sequence of these steps is |
| A. | 3, 2, 1, 4 |
| B. | 2, 3, 4, 1 |
| C. | 3, 1, 2, 4 |
| D. | 4, 3, 2, 1 |
| Answer» B. 2, 3, 4, 1 | |