The energy required per unit mass to grind limestone particles of very large size to 100 μm is 12.7 kWh/ton. An estimate (using Bond's law) of the energy to grind the particles from a very large size to 50 μrn is |
A. | 6.35 kWh/ton |
B. | 9.0 kWh/ton |
C. | 18 kWh/ton |
D. | 25.4 kWh/ton |
Answer» D. 25.4 kWh/ton | |