MCQOPTIONS
Saved Bookmarks
| 1. |
The earliest occurrence time for event 'I' is 8 weeks and the latest occurrence time for events 'I' is 26 weeks. The earliest occurrence time for evens '2' is 32 weeks and the latest occurrence time for events '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be: |
| A. | 11 |
| B. | 13 |
| C. | 18 |
| D. | 27 |
| Answer» D. 27 | |