1. |
The difference between costs linked to highest and lowest observation of cost driver is $27000 and observation of cost driver is 90 machine hours then slope coefficient is |
A. | $800 |
B. | $400 |
C. | $300 |
D. | $600 |
Answer» D. $600 | |