1.

The design capacity of channel/I-section purlin is given by

A. M = Z<sub>p</sub>/f<sub>y</sub>
B. M = Z<sub>p</sub> <sub>m0</sub>f<sub>y</sub>
C. M = Z<sub>p</sub> <sub>m0</sub>/f<sub>y</sub>
D. M = <sub>m0</sub>/f<sub>y</sub>
Answer» C. M = Z<sub>p</sub> <sub>m0</sub>/f<sub>y</sub>