1.

The correct sequence in the direction of the flow of water for installations in a hydropower plant is _______________________

A. Reservoir, Surge tank, Turbine, Penstock
B. Reservoir, Penstock, Surge tank, Turbine
C. Reservoir, Penstock, Turbine, Surge tank
D. Reservoir, Surge tank, Penstock, Turbine
Answer» C. Reservoir, Penstock, Turbine, Surge tank


Discussion

No Comment Found