MCQOPTIONS
Saved Bookmarks
1. |
The budgeted price of input is $70, actual quantity of input is 250 units and the allowed budgeted quantity of input is 90 units then efficiency variance is |
A. | $23,800 |
B. | $11,200 |
C. | $12,200 |
D. | $13,200 |
Answer» C. $12,200 | |