Statement (I): ‘Lift’ and ‘lead’, even if wherever relevant, do not affect any activity duration during the course of implementation of a project.Statement (II): Procurement of materials, particularly, is normally form assigned, or designated, quarry sites, which are already fixed while starting the project. |
| A. | Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I) |
| B. | Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I) |
| C. | Statement (I) is true but Statement (II) is false |
| D. | Statement (I) is false but Statement (II) is true |
| Answer» E. | |