1.

Shreya completes a work in one day and 6 hours while Shridha completes the same work in 2 days and 12 hours. How long will they take to complete the work if they work together?

A. 10 hrs
B. 20 hrs
C. 15 hrs
D. 5 hrs
Answer» C. 15 hrs