| 1. |
Several sequencing rules can be used to sequence jobs. The performance of these rules can be studied using several performance measures. Consider the following sequencing rules: SPT (Shortest Processing Time)EDD (Expected Due Date)and the following performance measures: MFT (Mean Flow Time) ML (Mean Lateness) Which one of the following is not correct? |
| A. | SPT minimizes MFT |
| B. | EDD minimizes MFT |
| C. | EDD minimizes ML |
| D. | SPT minimizes ML |
| Answer» E. | |