S, M, E and F are working in shifts in a team to finish a project. M works with twice the efficiency of others but for half as many days as E worked, S and M have 6 hour shifts in a day, whereas E and F have 12 hours shifts. What is the ratio of contribution of M to contribution of E in the project? |
| A. | 1 : 1 |
| B. | 1 : 2 |
| C. | 1 : 4 |
| D. | 2 : 1 |
| Answer» C. 1 : 4 | |