| 1. |
Removal of props under |
| A. | slabs spanning upto 4.5 m is 7 days |
| B. | slabs spanning more than 4.5 m is 14 days |
| C. | beams spanning upto 6 m is 14 days |
| D. | beams spanning more than 6 m is 21 days |
| E. | all the above. |
| Answer» F. | |