| 1. |
Rathin & Bratin together can complete a piece of work in 12 days. They start the work together but Rathin had to leave 5 days before the work got over. As a result it took a total of 15 days to complete the work. How many days would it have taken Bratin to complete the work by himself? |
| A. | 20 |
| B. | 24 |
| C. | 30 |
| D. | 28 |
| Answer» D. 28 | |