Q: X, Y and Z take 18 days to complete a piece of work. If X works alone he finishes the work in 36 days and if Y works alone he finishes it in 60 days. How long will it take Z to complete the work alone? |
A. | 78 days |
B. | 90 days |
C. | 96 days |
D. | 114 days |
Answer» C. 96 days | |