1.

Q: The project life cycle can be broken into five phases that tend to overlap with each other frm one phase to another;however ,the control phase does not overlap with a specific phase. why?

A. Change control management is seperate from the other phases
B. Change control management has a plan that can be usede throughout the initiation, planning, execution, and closeout of the project
C. Because the project sponsor is responsible for change control management , the project manager is not involved with that phase of the project
D. Change control extends throughout the entire project from initiation to closeout
Answer» E.