Q: 150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped on the second day, four more workers dropped on third day and so on. It takes 8 more days to finish the work now, find the number of days in which the work was completed? |
A. | 28 |
B. | 24 |
C. | 25 |
D. | 30 |
Answer» D. 30 | |