1.

Process I requires 20 units of fixed cost and 3 units of variable costs per piece, while process II required 50 units of fixed costs and I units of variable cost per piece. For a company producing 10 pieces per day:

A. Process I should be chosen
B. Process II should he chosen
C. Either of the two processes should he chosen
D. A combination of process 1 and process II should be chosen
Answer» B. Process II should he chosen