Pick up the correct statement from the following with regards to C.P.M. network analysis of projects |
| A. | Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity |
| B. | Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity |
| C. | The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time |
| D. | All the above. |