Pick up the correct reason for making conceptual (or preliminary) estimate from the following: |
| A. | To have a check on a definitive cost estimate. |
| B. | To check qoutations from contractors and/or sub contractors. |
| C. | To compute target estimate for the owner while drawings and specifications are in initial stage. |
| D. | All of these. |
| Answer» E. | |