MCQOPTIONS
Saved Bookmarks
1. |
Which of the following is not a factor in the failure of the systems developments projects? |
A. | size of the company |
B. | inadequate user involvement |
C. | failure of systems integration |
D. | continuation of a project that should have been cancelled |
E. | None of the above |
Answer» B. inadequate user involvement | |