MCQOPTIONS
Saved Bookmarks
| 1. |
P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in_________days. |
| A. | 10 |
| B. | 9 |
| C. | 11 |
| D. | 12 |
| Answer» B. 9 | |