MCQOPTIONS
Saved Bookmarks
| 1. |
Match List-I (Production Control Function) with List-II (Explanation) and-select the correct answer using the code given below the lists: List-I (Production Control Function) List-II (Explanation) A. Bill of Materials (BOM) 1. A technique for determining the quantity and timing of dependent demand items B. Capacity Resource Planning (CRP) 2. A technique for determining personal and equipment capacities needed to meet the production objectives C. Material Requirement Planning(MRP) 3. Specific what end items are to be D. Master Production Schedule (MPS) 4. The part number and quantity required per assembly Codes: |
| A. | A\[\to \]4, B\[\to \]1, C\[\to \]2, D\[\to \]3 |
| B. | A\[\to \]3, B\[\to \]2, C\[\to \]1, D\[\to \]4 |
| C. | A\[\to \]4, B\[\to \]2, C\[\to \]1, D\[\to \]3 |
| D. | A\[\to \]3, B\[\to \]1, C\[\to \]2, D\[\to \]3 |
| Answer» D. A\[\to \]3, B\[\to \]1, C\[\to \]2, D\[\to \]3 | |