Keeping in view, the feasibility order of magnitude, the preliminary, conceptual or budget estimates, are prepared by : |
| A. | architect/engineer |
| B. | construction manager |
| C. | owner himself/herself |
| D. | construction manager |
| Answer» D. construction manager | |