In the given figure, the network of a project represents |
A. | activity of an excavation of a footing |
B. | activity of an excavation which starts at event No. 1 and ends at even No. 2 |
C. | activity of excavation which takes 8 units of time |
D. | none of these. |
Answer» D. none of these. | |