1.

In mud-phuska terracing with tile paving, bitumen is spread over the R.C.C. slabs at the rate of ________ of bitumen per m2 of the roof surface.

A. 0.7 kg
B. 1.7 kg
C. 2.7 kg
D. 3.7 kg
Answer» C. 2.7 kg