In _________ method, the piles are driven along both the sides of existing wall and the needle in the form of pile caps are provided through the existing one. |
A. | Pit method |
B. | Pile method |
C. | Miscellaneous method |
D. | Vibroflotation |
Answer» C. Miscellaneous method | |