In gating system design, which one of the following is the correct sequence in which choke area, pouring time, pouring basin and sprue sizes are calculated?

A. Choke area - pouring time - pouring basin -sprue
B. Pouring basin - sprue - choke area - pouring
C. Choke area - sprue - pouring basin ? pouring time
D. Pouring basin - pouring time - choke area - sprue
Answer» D. Pouring basin - pouring time - choke area - sprue