In gating system design, which one of the following is the correct sequence in which choke area, pouring time, pouring basin and sprue sizes are calculated? |
| A. | Choke area - pouring time - pouring basin -sprue |
| B. | Pouring basin - sprue - choke area - pouring |
| C. | Choke area - sprue - pouring basin ? pouring time |
| D. | Pouring basin - pouring time - choke area - sprue |
| Answer» D. Pouring basin - pouring time - choke area - sprue | |