In CPM, the cost slope is determined by |
| A. | <img src="/_files/images/mechanical-engineering/industrial-engineering-and-production-management/742-78-1.png"> |
| B. | <img src="/_files/images/mechanical-engineering/industrial-engineering-and-production-management/742-78-2.png"> |
| C. | <img src="/_files/images/mechanical-engineering/industrial-engineering-and-production-management/742-78-3.png"> |
| D. | <img src="/_files/images/mechanical-engineering/industrial-engineering-and-production-management/742-78-4.png"> |
| Answer» C. <img src="/_files/images/mechanical-engineering/industrial-engineering-and-production-management/742-78-3.png"> | |