In an NC machining operation, the tool has to be moved from point (5, 4) to point (7, 2) along a circular path with centre at (5, 2). Before starting the operation, the tool is at (5, 4). The correct G and N codes for this motion are

A. N010GO3X7.0Y2.0I5.0J2.0
B. N010GO2X7.0Y2.0I5.0J2.0
C. N010GO1X7.0Y2.0I5.0J2.0
D. N010GOOX7.0Y2.0I5.0J2.0
Answer» C. N010GO1X7.0Y2.0I5.0J2.0