In an excavation of 3,000 cubic meter of common earth for a canal project, 6 men can be effectively employed on the job. If an output of a man is taken as 100 cubic meter per day, the duration of excavation activity will be |
| A. | 5 days |
| B. | 6 days |
| C. | 7 days |
| D. | 8 days |
| Answer» B. 6 days | |