1. |
If the present value of cash in flows from a project is Rs4.50 crore, initial outlay is Rs3.75 crore then the net benefit cost ratio is |
A. | 0.17 |
B. | 0.20 |
C. | 0.75 |
D. | 0.83 |
Answer» C. 0.75 | |