If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
A.
4 days
B.
6 days
C.
10 days
D.
16 days
Answer» E.
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
<p>Consider the following statements for a power shovel:<br /> (i) Output can be increased by reducing the angle of swing for a given depth of cut.<br /> (ii) For a given angle of swing, output will be maximum at optimum depth of cut.<br /> (iii) Output can be increased by keeping the depth of cut less than optimum depth.<br /> (iv) Output can be increased by increasing the size of shovel.</p>
<p>A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be</p>
<p>In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having</p>
<p>The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively</p>
<p>Latest start of an activity is always</p>
<h2>Earliest finish of an activity is always</h2>
<h2>Critical path</h2>
<h2>In time-cost optimization of a project, crashing is done.</h2>
<p>CPM is</p>
<h2>The most popular type of organization used for Civil Engineering Constructions, is</h2>
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply