If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to: |
| A. | 18 weeks |
| B. | 14 weeks |
| C. | 56 weeks |
| D. | 40 weeks |
| Answer» B. 14 weeks | |